Traffic-signal controller procurement verification checklist

Planning aid for an enquiry or design package — not a product specification, certificate, wiring drawing or field-work method.

Intended host page: https://www.led-trafficlight.com/industry/traffic-signal-controller-selection-guide/
Prepared 24 November 2026 (Asia/Shanghai). Nanjing Gaoqiao Traffic Technology Co., Ltd.

Leave a field blank or mark HOLD when the supporting document is missing. Do not fill typical voltages, clearance times, radio range, battery autonomy, protocol names or certification conclusions from this form. This is not a circuit or wiring diagram.

A. Project scope

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
A1Identify the country or authority, the site type, and whether the work is a new installation, a replacement, or another stated arrangement (for example a temporary or private-road site).Country or authority; site type; work type. Do not enter a standard name unless the project actually names that document.Owner or responsible engineerProject brief; authority correspondenceProject-specific☐
A2State the supply scope to be quoted: the controller only, or a cabinet assembly that may also include an enclosure, terminals and protection equipment.Requested scope, and a note that the contents of the selected listing must be confirmed on the quotation. Do not treat an output-count label as a complete bill of materials.Owner or responsible engineer; supplier confirms what the offer includesEnquiry text; quotation inclusions and exclusionsProcurement scope, not a regional code☐
A3State whether existing detectors, push-buttons, signal heads or a cabinet will be reused, and who is responsible for the condition of reused equipment.Reuse list; responsible party; items that have not yet been inspected.Owner or responsible engineerSite photographs; current drawings; written assumption listProject-specific☐
A4Record quantity, delivery location and project timetable so that a quotation can be checked against the actual shipment, not only against a product photograph.Quantity; destination; timetable if known. These are logistics fields, not performance claims.Owner or purchaserEnquiry; logistics instructionsProject-specific☐
A5Name the site power and cabling class: a mains or wired cabinet installation, or a solar / cable-limited installation.Class of installation only. Do not fill radio range, wireless protocol or battery autonomy on this line.Owner or responsible engineerSite brief; if solar or wireless, use the dedicated solar/wireless controller page for the remaining questionsSite constraint, not a product rating☐

B. Movement / phase or stage plan

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
B1Attach the junction layout or approved site drawing and record its document revision.Drawing title, revision and date. A one-page movement diagram is enough to start; it does not have to be a final wiring drawing.Owner or responsible engineerLayout or approved drawingProject-specific☐
B2Show each vehicle, pedestrian and (if used) bicycle movement, the clearance relationships, and any special condition such as a protected turn or a time-of-day mode.Movements, conflicts and special conditions. Do not start by counting lamps.Owner or responsible engineerPhase, stage or movement diagram — use the term defined in B3Project-specific☐
B3Name the official or authority document that defines the project's terms, and write the terms actually used on the schedule.For a United States project that uses MUTCD language, a signal phase is the right-of-way, yellow change, and red clearance intervals in a cycle assigned to an independent traffic movement or combination of movements (MUTCD 11th Edition, Revision 1, §1C.02 item 239). For a Great Britain project that uses Traffic Signs Manual Chapter 6 language, a phase can be thought of as a unique electrical circuit from the controller to one or more signal heads, and a stage can be defined as a period of time when one or more non-conflicting phases are given a green signal at the same time (TSM Chapter 6, 2019, §§6.3.1 and 6.4.1). Other authorities: name their document. Leave this line marked HOLD if the document is not yet named.Owner or responsible engineerNamed official or authority document, with edition or revisionUnited States, Great Britain, or another named authority — never as a global default☐
B4Do not translate a United States phase-and-movement schedule into a United Kingdom phase list, or the other way around, by name alone.Confirmation that the schedule uses the same term set as the controller worksheet and the governing document.Owner or responsible engineer; supplier checks the offer against that term setSchedule; controller configuration worksheetCross-jurisdiction projects in particular☐
B5Do not enter generic yellow, all-red, walk, pedestrian-change or intergreen times on this form.Leave timing values on the authority-approved plan. If a value is required for quotation, copy it only from that approved document and record the source. If no approved value exists, mark HOLD.Owner or responsible engineerApproved timing or intergreen document, if anyBy the named authority only; not a global typical value☐

C. Signal groups / outputs

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
C1List every independently switched indication the site requires, including vehicle, arrow, pedestrian, bicycle, countdown, warning-lamp or auxiliary-sign groups where they are used.One line for each independently controlled group, with a reference to the approved plan.Owner or responsible engineerSignal-group or output scheduleProject-specific☐
C2Treat shared output channels as a design decision, not as a way to shorten the enquiry. Outputs may share a channel only when the approved design permits it.Which groups, if any, are proposed to share a channel, and the design reference that permits it.Owner or responsible engineerApproved design; output scheduleOnly if the approved design allows sharing☐
C3Do not use a catalogue output count (for example a listing label) as the first selection factor, and do not treat that number as a verified capacity for every controller.The output count to be confirmed against the quoted model documents after the plan exists. Leave blank until those documents are in hand.Owner prepares the plan; supplier confirms the quoted revisionQuoted model datasheet or drawing; not a catalogue photographProcurement practice☐
C4Record load, voltage and switching-method requirements only from the project package and from the documents for the quoted revision.Values and units with the document title and revision. If those documents are not available, mark HOLD. Do not copy typical voltage lists from other web pages onto this line.Owner states site power design; supplier states the quoted revisionProject electrical design; quoted model documentsProject-specific; no default parameter☐
C5Identify whether the offered assembly uses an integrated output stage or separate load switches or drivers, where that distinction applies, and which terminals carry interface signals versus lamp load.Arrangement as shown on the quoted revision drawing. Leave blank if the drawing is not yet provided.Supplier, against the customer's scheduleWiring or interface drawing for the quoted revisionAs applicable to the offer☐

D. Detector and request inputs

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
D1Record which road users or functions must be able to place a call or a request (vehicles, pedestrians, bicycles, and any special inputs such as priority or cabinet status).User classes and special inputs, referenced to the approved plan.Owner or responsible engineerDetection or request planProject-specific☐
D2Give each detector input, pedestrian or bicycle request, preemption or priority input, and cabinet-status input its own line. Do not bury a push-button request in the same row as a vehicle presence call.Separated input schedule lines.Owner or responsible engineerI/O schedulePlanning practice☐
D3For every input, record together: the interface class, the event meaning, and the failure state. Electrical or communications limits belong on the same line only when they come from the documents for the exact revisions under review.Interface class (for example a contact or isolated output, or a serial or network message); event meaning (for example a call, an extension, a request, a fault or a heartbeat); failure state. 'Contact output' or 'RS-485' alone is not enough.Owner defines the required meaning; supplier maps the quoted revisionI/O schedule; detector and controller documents for the quoted revisionsPlanning practice; see the detector-inputs guide for the interface discussion, not for product ratings☐
D4Record any pulse, presence or message mode separately from the physical interface. Do not treat presence as automatically the same as an occupancy measurement, and do not treat a fieldbus name as a complete protocol specification.Mode or message set, with the document that defines it. No default hold time or sensitivity value.Owner or responsible engineer; supplier if providing detector electronicsDetector-unit or interface document for the quoted revisionWhere a detector electronics unit is used; U.S. handbook practice is informative only☐
D5Do not use the detector-input count to establish the number or load rating of independently switched outputs, or the other way around.Confirmation that the input list and the output list describe the same intersection.Owner or responsible engineerI/O schedule compared with the approved planPlanning practice☐

E. Interface compatibility

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
E1Compare the site power design with the input and output voltage of the quoted revision, using those documents only.Site voltage and the quoted-revision voltage, each with a source. Mark HOLD if either source is missing. Do not assume that a controller described only as '220 V' can operate a different signal voltage.Owner states site design; supplier states the quoted revisionElectrical design; quoted model documentsProject-specific; no typical voltage table on this form☐
E2Record the wiring common, any countdown timing source, and any communications or remote-supervision method as project requirements, not as assumed product features.Requirement and the document that defines it. Leave protocol names blank unless the project or the quoted-revision document actually names them.Owner or responsible engineer; supplier confirms the offerInterface requirement; quoted revision drawingProject-specific. Detailed head-to-controller checks belong on the compatibility guide, which is not re-audited in this pack.☐
E3For a replacement controller, collect photographs of labels and terminal layouts, the current wiring diagram, and a written assumption list for anything that cannot yet be inspected.Photograph or drawing references; open assumptions.Owner or installer provides site evidence; supplier states reuse conditionsPhotographs; existing wiring diagram; assumption listReplacement projects☐
E4If the project names a cabinet or controller family or standard (for example a stated NEMA TS 2 or ATC document in United States procurement), record it as a document requirement.Exact document title and revision required by the project. This line is not evidence that any particular model implements that standard.Owner or responsible engineer names the requirement; supplier states what is offered against itProject specification; any certificates only if later supplied for the quoted revisionOnly if the project names the document; United States families are not global rules☐
E5If solar operation, wireless coordination or connection to a central system is requested, record the function required and keep the detailed questions on the dedicated solar/wireless or communications discussion, not as filled-in range, protocol or autonomy figures on this form.Function requested; pointer to the dedicated page or specification. Mark HOLD for unconfirmed range, protocol and autonomy.Owner or responsible engineerFunctional requirement; later, documents for the quoted revisionOnly if that function is in scope☐

F. Failure states

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
F1For each input, record what the controller is expected to do if a required call is missing, if a call remains stuck, or if a detector or communications link is lost, and how recovery is recognized.Intended behaviour and the observation that would show it. No generic timing value.Owner or responsible engineer defines the required behaviour; supplier maps the quoted revisionI/O schedule; quoted revision documentsProject-specific☐
F2If remote supervision or coordination is in scope, record the required behaviour after a communication failure.Required behaviour and the document that defines it. Mark HOLD if it has not been defined.Owner or responsible engineerCommunications or coordination requirementOnly if communications are in scope☐
F3Do not use this checklist as a live-cabinet work instruction, a bypass method, or a permission to change safety timing on site.Confirmation that field diagnosis, if required, will follow the responsible authority and the approved method. This pack only asks what should be observable in an acceptance record.Owner, contractor and supplier as defined by the contractContract or method statement, if any; not this formSafety boundary for this pack☐

G. Document pack

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
G1Owner or engineer: approved detection plan and movement, phase or stage diagram, with revision.Document titles and revisions.Owner or responsible engineerApproved plan setProject-specific☐
G2Owner or engineer: the local documents that govern timing, accessibility and cabinet practice, identified by jurisdiction — not by a global default.Document titles and jurisdictions. Leave blank rather than inventing a default code.Owner or responsible engineerNamed local or national documentsBy jurisdiction☐
G3Owner or engineer: the drawings and test records that will be required at quotation, sample approval and commissioning.List of required deliverables at each stage.Owner or responsible engineerEnquiry or specificationProject-specific☐
G4Supplier: model, firmware or hardware revision, and the current wiring or interface drawing for that revision.Model and revision identifiers; drawing number.SupplierOffer documents for the quoted revision onlyAs applicable to the offer☐
G5Supplier: datasheet values for the offered input and output circuits (voltage, current, isolation, connector) taken only from those documents.Values with document title and revision, or HOLD if the datasheet is not in hand. This pack does not publish a company-wide rating.SupplierDatasheet or drawing for the quoted revisionQuoted revision only☐
G6Supplier: a marked-up I/O map that matches the customer's schedule, with exceptions written down.Map reference; list of exceptions.SupplierMarked I/O mapAs applicable to the offer☐
G7Supplier: a list of items included and excluded (for example detector units, racks, buttons, heads, cabinet, conflict monitor, communications devices, as applicable).Inclusion and exclusion list. Do not infer contents from an output-count label.SupplierQuotation bill of materialsAs applicable to the offer☐

H. Acceptance evidence

IDCheck itemWhat to recordResponsible partyEvidence / documentApplicabilityStatusNotes
H1Request the final controller configuration, a test record, a cable schedule and an as-built drawing for handover to the maintenance team. Do not leave the operating sequence to be interpreted only on site.Deliverable list and the revision that was actually shipped.Supplier prepares; owner or engineer acceptsConfiguration file or printout; test record; cable schedule; as-built drawingCommissioning records☐
H2Request acceptance tests that a witness can repeat for valid calls, missing calls, stuck inputs, lost links and recovery, as those events apply to the approved plan.Test names and the observations that count as a pass. No default pass/fail timings on this form.Owner specifies the required observations; supplier proposes the test record for the quoted revisionWritten test recordAs applicable to the approved plan☐
H3Request a parameter backup, or an equivalent record, for the delivered configuration.Backup identifier or file reference.Supplier prepares; owner retainsParameter backup or printed configurationAs applicable to the offer☐
H4Treat a test that passed on one configuration as covering only that configuration. A different input type, output load, firmware revision or reused field device needs its own record.The exact configuration covered by the record.Owner or responsible engineerTest record scope statementPlanning practice☐
H5Mounting height, sight distance and safety clearance times are not filled as numbers on this checklist. They remain on the authority-approved drawings.A pointer to the approved drawing, or HOLD if that drawing is not yet issued. No typical dimension or second count.Owner or responsible engineerAuthority-approved drawingsBy the named authority only☐